If you are finding a useful and valid training torrent for your preparation for CMAA Construction-Manager examination, our exam preparation files will be your best choice. Our exam materials are specially designed for all candidates to ensure you 100% pass rate and get CMAA certificate successfully. Compared with some study materials in other companies, our Construction-Manager study materials have a large number of astonishing advantages. Our Construction-Manager test questions and answers are tested for many times by our professionals who have been engaged in this field for 10 years. These questions of Construction-Manager practice test almost are collected and chosen from the previous exam pool and cover all key points which are vital for all candidates who can make a full preparation for the exam. So our Construction-Manager study materials are definitely the excellent goods for you with high-quality and high pass rate for your study. Now please pay much attention to more shining points about our Construction-Manager test questions.
Free renewal in one year
In order to cater to our customers, our company offers free renewal of Construction-Manager test questions to keep them the latest questions within one year. Our experts will spare no efforts to gather and update Construction-Manager practice test and compile these useful Construction-Manager study materials into preparation files. In this way we can not only miss any new information about the exam, but also provide efficient tips to you. Therefore, we can be confident enough to say that it is easy for you to pass CMAA Construction-Manager exam and gain the certificate.
Fast delivery after payment
Once you make a purchase for our Construction-Manager test questions, you will receive our Construction-Manager practice test within five minutes. You know, time is the most valuable for all people who make preparations for the test, no matter you are the working generation or students. Therefore, fast delivery is very vital for them. The moment you get our Construction-Manager study materials, you can take full advantage of them as soon as possible. I promise you will enjoy a satisfying and instant study which is never imagined before. So don't hesitate to join us, we will give you the most wonderful experience of study.
100% guarantee pass. No help, full refund
To help all of you to get the most efficient study and pass CMAA Construction-Manager the exam is the biggest dream we are doing our best to achieve. For us, customer is god. We will do our utmost to meet their requirement. Therefore, our experts will make great efforts to design and analyze questions and answers of Construction-Manager practice test which are more easily understood by our customers. In this way, our customers can have a good command of the knowledge about the Construction-Manager exam in a short time and then they will pass the exam in an easy way. Therefore you can definitely feel strong trust to our superior service. Unfortunately, if you fail in gaining the CMAA certificate with Construction-Manager study materials, you can require for changing another exam questions for free or ask for refund. You have no need to worry about your money. If you really want to take your money back, you just need to show your failure grade to us, and then we will refund you.
CMAA Certified Construction Manager (CCM) Sample Questions:
1. Contract administration includes, but is not limited to, planning for implementation of drawings, specifications, and
A) owner's scope of work.
B) standards.
C) permits.
D) licenses.
2. A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month
10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.
Which statement most accurately portrays program status?
A) Behind schedule, pay application accurately reflects percentage complete.
B) On schedule, pay application exceeds percentage complete.
C) On schedule, pay application accurately reflects percentage complete.
D) Behind schedule, pay application exceeds percentage complete.
3. A CM is milling and paving a 2-mile-long bridge with a surface that is in total failure. The owner gave the contractor October 24 as the fixed completion date. Meanwhile, the owner has promised the public that work hours would be 7am-7pm, 5 days per week and that the bridge would be completed by September 1.
The bridge deck is poured on a steel grid deck, but this type of operation has never been performed in the state and complications from weather have slowed progress. The contractor has requested to work nonstop 24/7 to meet the deadline told to the public.
The CM should
A) discuss with the owner and tell the contractor to do only 1/2 of the bridge.
B) tell the contractor they have until September 1 and can only work 7am-7pm.
C) meet with the owner and contractor to vet all issues/options and make a decision.
D) meet with the contractor to go over realistic time frames and make a decision.
4. When applying Business Intelligence (also known as data mining) to manage large volumes of construction project data, the source data must
A) include advanced algorithms.
B) first exist in hard copy format.
C) first exist in digital format.
D) include outliers and missing data.
5. During the design review process for a rehabilitation of a corporate office headquarters, the CM should routinely review the designers' submissions, and the reviews will include
A) constructability, biddability, and operability reviews.
B) budget, schedule, and value engineering reviews.
C) scope, constructability, and biddability reviews.
D) constructability, schedule, and maintenance reviews.
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: A | Question # 3 Answer: C | Question # 4 Answer: C | Question # 5 Answer: A |