NEW QUESTION # 20
What are dashboard alerts calculations based on?
- A. Percentage values
- B. Business Add-in (BAdi) implementation
- C. The status fields
- D. Numeric values (Specified range)
Answer: D
NEW QUESTION # 21
You have configured a new consultant role type, when you create a new role for a project, the consultant role type is not available for selection.
How do you make this selection available?
- A. Run a report to enable the consultant role type
- B. Assign the consultant role type to the appropriate project type
- C. Assign the consultant role type to the appropriate item type
- D. Activate the consultant role type
Answer: B
NEW QUESTION # 22
When are decision points for portfolio items created?
- A. After planning of financial values of an item
- B. During master date maintenance of an item
- C. After approval of an item
- D. During creation of an item
Answer: D
NEW QUESTION # 23
What features does SAP analytics cloud deliver in combination with SAP PPM?
NOTE: There are 3 correct answers to this question.
- A. Out-of-the-box cost commitment reporting capabilities
- B. Intelligent algorithms highlighting possible data quality issues and distributing your data
- C. Smart transformations enabling you to quickly address and solve data quality issues
- D. Provides models for financial and capacity planning
- E. Built-in connectors to data sources
Answer: B,C,E
NEW QUESTION # 24
Your client wants to add additional checklist items to a project that has already began. They want to control the items separately as unplanned.
Which setting must you make in customizing?
- A. Create a checklist type and assign a new status Unplanned
- B. Create a checklist item type and set the issue item indicator
- C. Create a checklist type and set the issue list indicator
- D. Create a checklist item type and assign to the project type
Answer: C
NEW QUESTION # 25
What data influence the bottom-up scheduling of a project in portfolio management?
NOTE: There are 3 correct answers to this question.
- A. Relationships between phases
- B. Relationships between tasks
- C. Duration of tasks
- D. Project type
- E. Role demands
Answer: A,B,C
NEW QUESTION # 26
What innovation management object is linked to SAP portfolio and project management (PPM) out of the box?
- A. Request
- B. Idea
- C. Opportunity
- D. Campaign
Answer: B
NEW QUESTION # 27
You have created a portfolio with the bucket levels and wants to create a portfolio item.
When can you create the portfolio item?
- A. At the lowest bucket level
- B. At any bucket level
- C. At the highest bucket level
- D. At multiple bucket levels
Answer: A
NEW QUESTION # 28
How do you make a decision point field a required field for a specific portfolio item?
- A. Make the filed a required field for the combination point and assign the item and decision point in customizing for the portfolio type
- B. Make the field a require field for the combination of decision point and portfolio type in customizing for the item type
- C. Make the filed a required field for the combination of the item and decision point in customizing for the portfolio type
- D. Make the filed a required field for the decision point and assign the item type to the portfolio In customizing
Answer: C
NEW QUESTION # 29
Which of the following multi-currency scenario are supported?
NOTE: There are 2 correct answers to this question
- A. Multiple planning currencies can be used in one bucket
- B. Items In a bucket an only use bucket currencies
- C. Item currency can be inherited from the assigned bucket
- D. Bucket in a portfolio can use different currencies
Answer: C,D
NEW QUESTION # 30
One of the tasks of your project has subtasks. You wants to restrict time recording to the subtasks.
How can you achieve this in customizing?
- A. Deactivate the mirrored task indicator for the project type
- B. Activate task hierarchies with summarization
- C. Activate task hierarchies without summarization
- D. Deactivate time recording for tasks
Answer: C
NEW QUESTION # 31
Where can you use stakeholders in portfolio management?
- A. Review
- B. Bucket
- C. Initiative
- D. Item
Answer: C
NEW QUESTION # 32
In SAP Enterprise Portfolio and Project Management, which objects can be used to exchange data back and forth to other application objects? Note: There are 2 correct answers to this question
- A. Milestone task and WBS element
- B. Portfolio item and Project System project definition
- C. Project phase and WBS element
- D. Project task and network activity
Answer: B,C
NEW QUESTION # 33
When you confirm a task, you wants the system to calculate the difference between planned work and actual work.
What must you do?
- A. Confirm the task using a completion percentage of less than 100
- B. Ensure that the Rem. Work manually indicator is inactive
- C. Enter an actual finish date of the task in the future
- D. Set the task status to in process
Answer: B
NEW QUESTION # 34
Where can you use the BCV report in SAP PPM?
NOTE: There are 3 correct answers to this question.
- A. Item
- B. Metrics
- C. Review
- D. Scoring model
- E. Bucket
Answer: A,C,E
NEW QUESTION # 35
Resources are not shown in the Resource Overview
What is the reason for this?
NOTE: There are 2 correct answers to this question
- A. Resource pool assignment is missing
- B. Project response assignment
- C. Staffing manager assignment is missing
- D. Assignment of resource management authorization object is missing
Answer: A,C
NEW QUESTION # 36
......