NEW QUESTION # 26
You want to split the financial planning values of portfolio item into two different buckets.
How do you do this?

  • A. Enable process change for multiple buckets.
    * Start process change to reassign the item two buckets
    * Maintain factors to split financial planning of the item
  • B. Enable the split of financial values for the item type
    * Assign the item to two bucket of the portfolio
    * Maintain factors to split financial planning of the item
  • C. Enable the split of financial values for the item type.
    * Assign the item to two bucket of the classification hierarchy
    * Maintain factors to split financial planning of the item
  • D. Enable financial planning for multiple buckets
    * Assign additional buckets in financial planning
    * Maintain factors to split financial planning of the item.

Answer: B


NEW QUESTION # 27
Which system behavior are enabled when a create a project with multiple phase?
NOTE: There are 2 correct answers to this question.

  • A. Determination of the start-dates of subsequent phases
  • B. Rollup of resource requirements of tasks to phases
  • C. Rollup of activity cost allocations to phases
  • D. Determination of the start- and end-dates of tasks

Answer: A,D


NEW QUESTION # 28
For which of the following object types can you define questionnaires? NOTE: There are 2 correct answers to this question

  • A. Project management project
  • B. Initiative
  • C. Bucket
  • D. Portfolio item

Answer: B,D


NEW QUESTION # 29
You have defined a financial view for portfolio bucket so that financial values are rolled up.
Which of the following are possible sources for the rollup?
NOTE: There are 3 correct answers to this question

  • A. Standalone items
  • B. Project system project
  • C. Project management projects
  • D. Initiatives

Answer: A,D


NEW QUESTION # 30
Which of the following can you use to create multiple portfolio items simultaneously?

  • A. Item template
  • B. Microsoft project import
  • C. Primavera import
  • D. Microsoft Excel import

Answer: D


NEW QUESTION # 31
Which cost planning process can you use at item level?
NOTE: There are 2 correct answers to this question.

  • A. Manual cost planning
  • B. Rollup of cost planning
  • C. Integrated cost planning
  • D. Hierarchical cost planning

Answer: A,C


NEW QUESTION # 32
In a existing project management project, all objects have been released and all subordinate tasks for the checklist items have been completed.
Why does the status change fail when you try to set the status of the checklist to Finish?
How can you trigger a workflow for a portfolio item?

  • A. A checklist item is still open
  • B. At least of the tasks has been configured
  • C. You are missing the authorization for changing the project
  • D. The checklist item result is set to not ok

Answer: C,D


NEW QUESTION # 33
Which of the following are valid breakdown periods for financial planning in Portfolio Management?
Note: There are 2 correct answers to this question

  • A. 2 weeks
  • B. 1 year
  • C. 10 days
  • D. 3 months

Answer: B,D


NEW QUESTION # 34
How can you trigger a workflow for a portfolio item? NOTE: There are 2 correct answers to this question.

  • A. Exceed the budget of the item
  • B. Change the master data of the item
  • C. Choose the start workflow button
  • D. Change the item status

Answer: C,D


NEW QUESTION # 35
What can you use scoring models for? NOTE: There are 2 correct answers to this question.

  • A. To compare bucket in reviews
  • B. Top compare items in reviews
  • C. To derive field values of items
  • D. To derive field values of buckets

Answer: B,C


NEW QUESTION # 36
You want to configure portfolio management to use Financial planning for manual planning on the item level.
Which of the following settings are required? NOTE: There are 2 correct answers to this question.

  • A. Cost element groups
  • B. Views
  • C. Value types
  • D. Categories

Answer: B,D


NEW QUESTION # 37
In SAP Enterprise Portfolio and Project Management, which objects can be used to exchange data back and forth to other application objects? Note: There are 2 correct answers to this question

  • A. Project phase and WBS element
  • B. Project task and network activity
  • C. Portfolio item and Project System project definition
  • D. Milestone task and WBS element

Answer: A,C


NEW QUESTION # 38
How can you connect an original file with a project management task?
NOTE: There are 2 correct answers to this question.

  • A. Create a link to a documents into record hierarchy that contains the file
  • B. Use the Create New Document function in project management and check in the file
  • C. Upload the original file using integration to a third party documents management system
  • D. Use Document services to create a link to the original file

Answer: A,B


NEW QUESTION # 39
You want to use a customer-specific status for items.
How do you configure the status in customizing?

  • A. Create the status and status transition within the portfolio type
    Assign the portfolio item type to the portfolio type
  • B. Create a business add-in (BAdi) for customer-specific status management Activate the BAdi for the portfolio item type
  • C. Create the status
    Assign the status to a portfolio item type
    Specify the status transitions with respect the portfolio item type
  • D. Create a status profile for the portfolio item objet type
    Create the status within the status profile
    Assign the status profile to a portfolio item type

Answer: C


NEW QUESTION # 40
What data influence the bottom-up scheduling of a project in portfolio management?
NOTE: There are 3 correct answers to this question.

  • A. Role demands
  • B. Relationships between phases
  • C. Project type
  • D. Relationships between tasks
  • E. Duration of tasks

Answer: B,D,E


NEW QUESTION # 41
What are valid breakdown period for financial planning in portfolio management? NOTE: There are 2 correct answers to this question.

  • A. Weeks
  • B. Years
  • C. months
  • D. Days

Answer: B,C


NEW QUESTION # 42
Which method can you use to update multiple values simultaneously in capacity planning for portfolio management?

  • A. Mass update
  • B. Distribution function
  • C. Drag and drop
  • D. XML upload

Answer: A


NEW QUESTION # 43
What influences whether an items is displayed in a specific dashboard scope? NOTE: There are 3 correct answers to this question

  • A. Escalation flag
  • B. Priority
  • C. Decision point status
  • D. Item status group
  • E. Proposal flag

Answer: A,C,D


NEW QUESTION # 44
......